Which change management process component is concerned with the cost and resources necessary for implementation?

Last Updated on March 23, 2021 by Admin

Which change management process component is concerned with the cost and resources necessary for implementation?

  • assessment
  • approval
  • implementation
  • identification
    Explanation:

    There are several change management process components that help changes, installations, and upgrades go more easily. The assessment component identifies the business processes that are affected and the costs and resources required.